This Week’s Activities
- Completed installation of paving stones for lower patios.
- Completed installation of low voltage lighting for ramps and lower right patios.
- Completed capping walls for lower patios.
- Completed kitchens and fireplaces for lower patios.
Next Week’s Planned Activities
- Cover trenches and reinstall sod.
- Test gas lines and get inspections.
- Begin backfilling around patio walls.
Current Safety Concerns
None.
Material Deliveries Scheduled
Any deliveries will be by small vehicles only
Comments
The Ernest Maier Crew tells us that they will have the railings for the ramps up and the patios and appliances available for use by the troops not later than April 1.