- Installed sod around the lower patios. Completed landscaping.
- Completed Walk of Appreciation and Gazebo base. Laid footers for Gazebo.
- Connected BBQs; all gas tests positive.
- Installed three kitchen tops and one fireplace hearth.
- Measured all ramps for railing.
- OPENED RAMPS—HELD A GREAT PARTY.
- Modify bluestone as necessary to complete kitchen tops, fireplace hearth.
- Turn on BBQs. Open to use.
- Complete installation of sod around entire area.
- Erect gazebo.
None
Material Deliveries Scheduled
Sod. Gazebo arrives Friday.
Comments
- OPENED RAMPS—HELD A GREAT PARTY.
- Thanks to The Difference, the Air Products Corporate Band.
- Thanks to Greg Casten, Pro Fish, and Kaufmann’s Tavern for the barbeque.
- Thanks to the Mologne House staff for all the great help.
- We plan to open the BBQs to the use of the troops and families on Monday.