- Graded all areas and installed sod around walkway near to Mologne House, between that walkway and the lower patio, and over the gas trenches.
- Completed base for walkways and gazebo. Started laying pavers on Walk of Appreciation between
- Gazebo and upper sidewalk.
- Connected valves to BBQs and one fireplace.
- Ordered landscaping.
- Ordered gazebo, for delivery on April 18.
Next Week’s Planned Activities
- Complete installation of sod.
- Complete laying pavers on walkways.
- Test all appliances. Turn on gas.
- Install kitchen counter tops. Install fireplace hearth, mantles, etc. if material is delivered.
None.
Material Deliveries Scheduled
Paving stones for walkways. Sod. Landscaping materials.
Comments
- Requested approval of temporary railing to open ramp, pending installation of permanent railing.
- We will open the upper patio BBQ for use this week, and lower patio BBQs if we receive Garrison approval of temporary railing.