Progress Report: April 6, 2008

This Week’s Activities
  • Graded all areas and installed sod around walkway near to Mologne House, between that walkway and the lower patio, and over the gas trenches.
  • Completed base for walkways and gazebo. Started laying pavers on Walk of Appreciation between
  • Gazebo and upper sidewalk.
  • Connected valves to BBQs and one fireplace.
  • Ordered landscaping.
  • Ordered gazebo, for delivery on April 18.

Next Week’s Planned Activities

  • Complete installation of sod.
  • Complete laying pavers on walkways.
  • Test all appliances. Turn on gas.
  • Install kitchen counter tops. Install fireplace hearth, mantles, etc. if material is delivered.
Current Safety Concerns

None.

Material Deliveries Scheduled

Paving stones for walkways. Sod. Landscaping materials.

Comments
  • Requested approval of temporary railing to open ramp, pending installation of permanent railing.
  • We will open the upper patio BBQ for use this week, and lower patio BBQs if we receive Garrison approval of temporary railing.