- Erected Gazebo. It looks great!!
- BBQs ready to go—awaiting final protocol from Mologne House management.
- Ordered fabrication of railing for walkway. Installation date: April 30.
- Second party weekend—thanks to Suffolk Police Veterans Association.
- Modify bluestone as necessary to complete kitchen tops, fireplace hearth.
- Complete installation of sod around entire area. Installation date: April 26.
- Install fireplace appliances, log sets and screens.
None.
Material Deliveries Scheduled
None.
Comments
- Second great party—thanks to Suffolk Police Veterans Association.
- We plan to open the BBQs to the use of the troops and families on Monday, pending issuance of protocol by Mologne House management.