Thursday, April 3, 2008

Progress Report: March 30, 2008

This Week’s Activities
  • Covered trenches, backfilled around patios and ordered sod.
  • Tested gas lines, inspected same.
  • Connected gas lines to three BBQs, prepared fireplaces for connection.
  • Excavated for upper walkways and gazebo. Began to lay base in these areas.
Next Week’s Planned Activities
  • Grade all covered areas and reinstall sod.
  • Complete base for walkways and gazebos. Start laying pavers.
  • Finish connecting BBQs. Connect valves in fireplaces. Test all appliances. Turn on gas.
  • Install sod in area around upper patio and lower left patio.
  • Order landscaping materials.
Current Safety Concerns

None.

Material Deliveries Scheduled

Base materials and paving stones for walkways and gazebo.

Comments

Placed temporary railing on ramp, pending installation of permanent ramp. Requesting inspection and determination of adequacy of temporary railing to open ramp.

0 comments: