- Covered trenches, backfilled around patios and ordered sod.
- Tested gas lines, inspected same.
- Connected gas lines to three BBQs, prepared fireplaces for connection.
- Excavated for upper walkways and gazebo. Began to lay base in these areas.
- Grade all covered areas and reinstall sod.
- Complete base for walkways and gazebos. Start laying pavers.
- Finish connecting BBQs. Connect valves in fireplaces. Test all appliances. Turn on gas.
- Install sod in area around upper patio and lower left patio.
- Order landscaping materials.
None.
Material Deliveries Scheduled
Base materials and paving stones for walkways and gazebo.
Comments
Placed temporary railing on ramp, pending installation of permanent ramp. Requesting inspection and determination of adequacy of temporary railing to open ramp.