Monday, March 24, 2008

Progress Report: March 16, 2008

This Week’s Activities
  • Completed installation of electric for lower patios.
  • Completed low voltage lighting for lower right patio, capped walls.
  • Dug gas trench and installed gas lines.
  • Installed access doors for kitchens on lower right patio.
  • Begin installing pavers for lower right patio.
  • Laid out final gazebo and walkway locations.
Next Week’s Planned Activities
  • Cover trenches and reinstall sod. Test gas lines and get inspections.
  • Complete installing pavers for lower right patio.
  • Begin facing fireplace with veneer stone.
  • Begin backfilling around patio walls.
Current Safety Concerns

None

Material Deliveries Scheduled

Any deliveries will be by small vehicles only.

Comments

The Ernest Maier Crew tells us that they will have the railings for the ramps up and the patios and appliances available for use by the troops not later than April 1.

No comments: