- Installed Engraved Paving Stones on Walk of Appreciation.
- Installed Paver Art in Gazebo. It looks great!!
- BBQs opened and used this weekend.
- Third party weekend—thanks to the Red River Valley River Rats and others.
- Completed installation of sod around entire area, except for one small portion.
- Complete installation of kitchen tops and fireplace hearths and mantles.
- Complete installation of fireplace appliances, log sets and screens.
- Install railings on all ramped walkways.
None.
Material Deliveries Scheduled
None.
Comments
- The work is 99% done.
- We will remove the last barriers to Courtyard access upon installation of the railings.GRAND OPENING—1400 hours, May 3, 2008