- Completed trench for electric lines for lower patios and ramp.
- Set final grades and removed last of dirt from lower right patio.
- Compacted soil and installed base for lower right patio in 2” lifts in lower right patio.
- Installed wire for low voltage lights in lower right patio.
- Installed block for fireplace and completed shells for kitchen islands in lower right patio.
Next Week’s Planned Activities
- Start fireplace installation in lower right patio.
- Install low voltage lights and start capping sit walls in lower right patio.
- Start installing sand and pavers in lower right patio.
Current Safety Concerns
NoneInjuries This Week
None
Material Deliveries Scheduled
Fireplace and sand mid week. Pavers towards end of week.
Comments
- Short week due to weather but lots of progress.
- Arborist/Horticulturist to review placement of gazebo on Tuesday.
- Final planning on layout for walkway and gazebo expected next week.
- Final planning on all wiring and lighting installation expected next week.