- Installed electric lines for both lower patios.
- Removed sod for gas trench and started digging trench for gas lines.
- All base installed and tamped on lower right patio.
- Lower right patio fireplace installed.
- Lower right patio kitchens ready for access doors and grills.
- Install low voltage lights and start capping sit walls for lower right patio.
- Start installing sand and pavers for lower right patio.
- Begin facing fireplace for lower right patio.
- Install gas lines in trenches, cover and reinstall sod.
- Install access doors and grills in kitchens in lower right patio.
- Begin backfilling around patio walls.
Sediment control issue was brought to the crew’s attention early in the week. Situation occurred as a result of the unusually heavy rains. Small amount of sand from the staging area that washed into the street was cleaned up immediately. Crew secured portions of safety fence that have been blown down.
Injuries This Week
None.
Material Deliveries Scheduled
Pavers, sand and veneer early in week.
Comments
All working on the site are committed to having the patios and appliances available for use by the troops not later than April 1.