Tuesday, March 4, 2008

Progress Report: March 2, 2008

This Week’s Activities
  • Installed fireplace unit for lower right patio.
  • Installed iron plate over manhole cover in south wall of lower right patio.
  • Put off installation of low voltage lights and capping walls in lower right patio.
  • Put off installation of sand and pavers in lower right patio.

Next Week’s Planned Activities

  • Install low voltage lights and start capping sit walls in lower right patio.
  • Start installing sand and pavers in lower right patio.
  • Begin facing fireplace for lower right patio.
  • Weather permitting, dig trench for gas pipes, and lay pipes from Mologne House to appliances in all patios.

Current Safety Concerns

None

Injuries This Week

None

Material Deliveries Scheduled

  • Several loads of CR6 throughout the week.
  • Pavers likely towards the end of the week.

Comments

  • Difficult week because of weather.
  • Three idle days.
  • Better weather forecast for next week.

No comments: