- Installed fireplace unit for lower right patio.
- Installed iron plate over manhole cover in south wall of lower right patio.
- Put off installation of low voltage lights and capping walls in lower right patio.
- Put off installation of sand and pavers in lower right patio.
Next Week’s Planned Activities
- Install low voltage lights and start capping sit walls in lower right patio.
- Start installing sand and pavers in lower right patio.
- Begin facing fireplace for lower right patio.
- Weather permitting, dig trench for gas pipes, and lay pipes from Mologne House to appliances in all patios.
Current Safety Concerns
None
Injuries This Week
None
Material Deliveries Scheduled
- Several loads of CR6 throughout the week.
- Pavers likely towards the end of the week.
Comments
- Difficult week because of weather.
- Three idle days.
- Better weather forecast for next week.