Progress Report: March 16, 2008

This Week’s Activities
  • Completed installation of electric for lower patios.
  • Completed low voltage lighting for lower right patio, capped walls.
  • Dug gas trench and installed gas lines.
  • Installed access doors for kitchens on lower right patio.
  • Begin installing pavers for lower right patio.
  • Laid out final gazebo and walkway locations.
Next Week’s Planned Activities
  • Cover trenches and reinstall sod. Test gas lines and get inspections.
  • Complete installing pavers for lower right patio.
  • Begin facing fireplace with veneer stone.
  • Begin backfilling around patio walls.
Current Safety Concerns

None

Material Deliveries Scheduled

Any deliveries will be by small vehicles only.

Comments

The Ernest Maier Crew tells us that they will have the railings for the ramps up and the patios and appliances available for use by the troops not later than April 1.

Friday, March 14, 2008

Progress Report: March 9, 2008

This Week’s Activities
  • Installed electric lines for both lower patios.
  • Removed sod for gas trench and started digging trench for gas lines.
  • All base installed and tamped on lower right patio.
  • Lower right patio fireplace installed.
  • Lower right patio kitchens ready for access doors and grills.
Next Week’s Planned Activities
  • Install low voltage lights and start capping sit walls for lower right patio.
  • Start installing sand and pavers for lower right patio.
  • Begin facing fireplace for lower right patio.
  • Install gas lines in trenches, cover and reinstall sod.
  • Install access doors and grills in kitchens in lower right patio.
  • Begin backfilling around patio walls.
Current Safety Concerns

Sediment control issue was brought to the crew’s attention early in the week. Situation occurred as a result of the unusually heavy rains. Small amount of sand from the staging area that washed into the street was cleaned up immediately. Crew secured portions of safety fence that have been blown down.

Injuries This Week

None.

Material Deliveries Scheduled

Pavers, sand and veneer early in week.

Comments

All working on the site are committed to having the patios and appliances available for use by the troops not later than April 1.

Tuesday, March 4, 2008

Progress Report: March 2, 2008

This Week’s Activities
  • Installed fireplace unit for lower right patio.
  • Installed iron plate over manhole cover in south wall of lower right patio.
  • Put off installation of low voltage lights and capping walls in lower right patio.
  • Put off installation of sand and pavers in lower right patio.

Next Week’s Planned Activities

  • Install low voltage lights and start capping sit walls in lower right patio.
  • Start installing sand and pavers in lower right patio.
  • Begin facing fireplace for lower right patio.
  • Weather permitting, dig trench for gas pipes, and lay pipes from Mologne House to appliances in all patios.

Current Safety Concerns

None

Injuries This Week

None

Material Deliveries Scheduled

  • Several loads of CR6 throughout the week.
  • Pavers likely towards the end of the week.

Comments

  • Difficult week because of weather.
  • Three idle days.
  • Better weather forecast for next week.

Progress Report: February 24, 2008

This Week’s Activities
  • Completed trench for electric lines for lower patios and ramp.
  • Set final grades and removed last of dirt from lower right patio.
  • Compacted soil and installed base for lower right patio in 2” lifts in lower right patio.
  • Installed wire for low voltage lights in lower right patio.
  • Installed block for fireplace and completed shells for kitchen islands in lower right patio.

Next Week’s Planned Activities

  • Start fireplace installation in lower right patio.
  • Install low voltage lights and start capping sit walls in lower right patio.
  • Start installing sand and pavers in lower right patio.

Current Safety Concerns

None

Injuries This Week

None

Material Deliveries Scheduled

Fireplace and sand mid week. Pavers towards end of week.

Comments
  • Short week due to weather but lots of progress.
  • Arborist/Horticulturist to review placement of gazebo on Tuesday.
  • Final planning on layout for walkway and gazebo expected next week.
  • Final planning on all wiring and lighting installation expected next week.