Thursday, February 7, 2008

Progress Report: February 6, 2008

Today’s Activities
  • Completed north wall of lower right patio.
  • Dug footer dug on south wall of lower right patio.
  • Completed excavation for entire patio area.
  • Excellent progress today.
Tomorrow’s Planned Activities
  • Begin installing two outdoor kitchens on lower right patio.
  • Continue installing base for south wall of lower right patio.
  • Continue installing south wall.
Safety Concerns

None

Material Deliveries Scheduled

Possible trucks in and out all day removing dirt.

Comments
  • Many thanks to Don Chory for expediting resolution of difficult construction issues on lower right patio.
  • We are in need of donations for trucking for dirt removal.
  • If anyone has any leads, please contact Ken Cook. Thanks.