Thursday, February 7, 2008

Progress Report: February 5, 2008

Today’s Activities

  • Footer dug and poured for the fireplace for lower right patio.
  • Footer dug for north side wall on lower right patio.

Tomorrow’s Planned Activities

  • Block up fireplace for lower right patio.
  • Lay footer course for north side wall for lower right patio.

Current Safety Concerns

  • Moving equipment, material, and the drop from sidewalk to our excavation (5’ or more) for the lower right patio: that is, the sidewalk from the center of the Courtyard to the Playground area.
  • We cannot open the ramp until the safety of pedestrians can be assured.
    As lower right patio progresses, and the equipment and materials clear the area, we will review this issue
  • We want the ramp open for the residents as soon as possible, but not with safety risks.

Material Deliveries Scheduled

None

Comments

This is a team effort with two teams playing the same game, and we are appreciate the cooperation and advice of our WRAMC team. Thanks.

No comments: