Friday, February 15, 2008

Progress Report: February 12, 2008

Today’s Activities

  • Finished modifications to manhole cover under south wall of lower right patio.
  • Completed installation of south wall of lower right patio.
  • Cut grooves for lighting installation on lower right patio walls.
  • Removed significant dirt and debris from site.

Tomorrow’s Planned Activities

  • No work planned Wednesday. Bad weather coming. Resume work Thursday.
  • Continue blocking up fireplace on lower right patio.
  • Start work on wing walls for lower right patio access.
  • Begin lighting installation on lower right patio walls.

Current Safety Concerns

None

Material Deliveries Scheduled

None

Comments

  • No work planned Wednesday. Bad weather coming. Resume work Thursday.
  • Hand railing design approved today. We will install it as soon as we get it.