Today’s Activities
- Finished modifications to manhole cover under south wall of lower right patio.
- Completed installation of south wall of lower right patio.
- Cut grooves for lighting installation on lower right patio walls.
- Removed significant dirt and debris from site.
Tomorrow’s Planned Activities
- No work planned Wednesday. Bad weather coming. Resume work Thursday.
- Continue blocking up fireplace on lower right patio.
- Start work on wing walls for lower right patio access.
- Begin lighting installation on lower right patio walls.
Current Safety Concerns
None
Material Deliveries Scheduled
None
Comments
- No work planned Wednesday. Bad weather coming. Resume work Thursday.
- Hand railing design approved today. We will install it as soon as we get it.