- Began laying base for lower left patio.
- Complete inspection of sheathing of utilities for lower left patio.
- Continued work on walls for east side of ramp.
- Continued work on walls for lower right patio.
- Installed most of Bluestone in Upper Patio.
- Continue laying base for lower left patio.
- Continue work on walls for east side of ramp.
- Continue work on walls for lower right patio.
Continue to expect heavy loads of material during all work days in January.
Material Deliveries Scheduled
Light deliveries scheduled next week.
Comments
- Great work day today.
- We expect heavy work schedules this next week, as the weather predictions are very good.