- Completed prep for laying base for lower left patio.
- Continued work on walls for east side of ramp.
- Continued work on walls for lower right patio.
- Begin laying base for lower left patio.
- Complete inspection of sheathing of utilities for lower left patio.
- Continue work on walls for east side of ramp.
- Continue work on walls for lower right patio.
- None.
- Continue to expect heavy loads of material during all work days in January.
Light deliveries scheduled next week.
Comments
- We expect heavy work schedules this next week, as the weather predictions are very good.
- We are pleased with the progress on the ramp, hoping to meet our completion target of mid-January.