Monday, January 7, 2008

Progress Report: January 5, 2008

Today’s Activities
  • Completed prep for laying base for lower left patio.
  • Continued work on walls for east side of ramp.
  • Continued work on walls for lower right patio.
Tomorrow’s Planned Activities
  • Begin laying base for lower left patio.
  • Complete inspection of sheathing of utilities for lower left patio.
  • Continue work on walls for east side of ramp.
  • Continue work on walls for lower right patio.
Current Safety Concerns
  • None.
  • Continue to expect heavy loads of material during all work days in January.
Material Deliveries Scheduled

Light deliveries scheduled next week.

Comments
  • We expect heavy work schedules this next week, as the weather predictions are very good.
  • We are pleased with the progress on the ramp, hoping to meet our completion target of mid-January.

No comments: