- Completed west walls for ramp.
- Delayed resolution of sheathing issues for conduit pipes below surface of lower left patio to accommodate other contractor’s work.
- Delayed completion of prep work for base of lower left patio for same reason.
- Finished footers for east side of ramp; began work on east walls for ramp.
- Started digging footers for walls for lower right patio.
- Complete sheathing underground utilities for lower left patio.
- Complete prep work for base for lower left patio.
- Continue work on walls for east side of ramp.
- Continue digging footers for walls for lower right patio.
- None.
- Cold weather precautions in place.
- Continue to expect heavy loads of material during all work days in January.
Light deliveries scheduled rest of first week of January.
Comments
- We are on schedule and should meet our targets.
- We are taking cold weather precautions for the work crew.
- We expect heavy work schedules until completion of lower left patio and ramp, probably working weekends as long as we can.
- We expect to work this weekend, at least Saturday, to install bluestone kitchen countertop, fireplace hearth and fireplace mantle in Upper Patio.