Thursday, January 3, 2008

Progress Report: January 3, 2008

Today’s Activities
  • Completed west walls for ramp.
  • Delayed resolution of sheathing issues for conduit pipes below surface of lower left patio to accommodate other contractor’s work.
  • Delayed completion of prep work for base of lower left patio for same reason.
  • Finished footers for east side of ramp; began work on east walls for ramp.
  • Started digging footers for walls for lower right patio.
Tomorrow’s Planned Activities
  • Complete sheathing underground utilities for lower left patio.
  • Complete prep work for base for lower left patio.
  • Continue work on walls for east side of ramp.
  • Continue digging footers for walls for lower right patio.
Current Safety Concerns
  • None.
  • Cold weather precautions in place.
  • Continue to expect heavy loads of material during all work days in January.
Material Deliveries Scheduled

Light deliveries scheduled rest of first week of January.

Comments
  • We are on schedule and should meet our targets.
  • We are taking cold weather precautions for the work crew.
  • We expect heavy work schedules until completion of lower left patio and ramp, probably working weekends as long as we can.
  • We expect to work this weekend, at least Saturday, to install bluestone kitchen countertop, fireplace hearth and fireplace mantle in Upper Patio.

0 comments: