- Great start to the New Year.
- Finished all but one small portion of the walls for lower left patio.
- Completed west walls for ramp.
- Resolved sheathing issues for conduit pipes below surface of lower left patio.
- Dug footers for east walls for ramp.
- Complete sheathing underground utilities for lower left patio
- Complete prep work for base for lower left patio.
- Complete walls for lower left patio.
- Finish footers for east side of ramp.
- None.
- Cold weather precautions in place.
- Continue to expect heavy loads of material during all work days in January.
Light deliveries scheduled rest of first week of January.
Comments
- We are on schedule and should meet our targets.
- We are taking cold weather precautions for the work crew.
- We expect heavy work schedules until completion of lower left patio and ramp, probably working weekends as long as we can.