Thursday, January 3, 2008

Progress Report: January 2, 2008

Today’s Activities
  • Great start to the New Year.
  • Finished all but one small portion of the walls for lower left patio.
  • Completed west walls for ramp.
  • Resolved sheathing issues for conduit pipes below surface of lower left patio.
  • Dug footers for east walls for ramp.
Tomorrow’s Planned Activities
  • Complete sheathing underground utilities for lower left patio
  • Complete prep work for base for lower left patio.
  • Complete walls for lower left patio.
  • Finish footers for east side of ramp.
Current Safety Concerns
  • None.
  • Cold weather precautions in place.
  • Continue to expect heavy loads of material during all work days in January.
Material Deliveries Scheduled

Light deliveries scheduled rest of first week of January.

Comments
  • We are on schedule and should meet our targets.
  • We are taking cold weather precautions for the work crew.
  • We expect heavy work schedules until completion of lower left patio and ramp, probably working weekends as long as we can.

0 comments: