Progress Report: January 14, 2008

Today’s Activities
  • Laid paving stones over half of lower left patio.
  • Continued to truck out excess dirt in lower right patio area.
  • Completed walls for east side of ramp.
  • Began prep work for base on ramps.
Tomorrow’s Planned Activities
  • Continue to lay paving stones in lower left patio.
  • Continue work on walls for lower right patio.
  • Continue prep work for base on ramps.
Current Safety Concerns

None.

Material Deliveries Scheduled

Expect heavy deliveries of stone and base materials over the next few days.

Comments
  • We appreciate the assistance of all the WRAMC staff in solving minor underground issues in the lower patios. We are confident in the solutions.
  • We are sure that we will stay on schedule, if the weather holds.
  • We appreciate the comments from visitors to the site about the mantle and countertop and we are ordering materials that have rounded or beveled edges to replace the sharp edges that are now there. Thanks.