- Short work day today—rained out at noon.
- Finalized sand base for lower left patio, covered all with canvas.
- Continued work on walls for lower right patio.
- Moved temporary fencing around staging area away from sidewalks and secured it better.
- Begin laying paving stones on lower left patio.
- Continue to truck out excess dirt in lower right patio area.
- Complete walls for east side of ramp.
- Continue work on walls for lower right patio.
- Begin prep work for base on ramps.
None.
Material Deliveries Scheduled
- Expect more trucks to haul out excess dirt from lower right patio.
- Expect heavy deliveries of stone and base materials over the next few days.
- Good progress this week despite rainy conditions at end of week.
- We appreciate the constant advice and support from all aspects of our WRAMC team, especially our liaison SPC John Williams and COL Doherty’s colleagues.