Sunday, January 13, 2008

Progress Report: January 10, 2008

Today’s Activity

  • Screed base for lower left patio.
  • Finalize sand base for lower left patio.
  • Completed most of walls for east side of ramp.
  • Continued work on walls for lower right patio.
  • Moved temporary fencing around staging area.
  • Trucked out excess dirt in lower right patio area.

Tomorrow’s Planned Activities

  • Continue to truck out excess dirt in lower right patio area.
  • Complete walls for east side of ramp.
  • Continue work on walls for lower right patio.

Current Safety Concerns

Moved temporary fencing around staging area.

Material Deliveries Scheduled

  • No deliveries scheduled tomorrow.
  • Expect trucks to haul out excess dirt from lower right patio.

Comments

Good progress despite rainy conditions.

No comments: