Progress Report: November 30, 2007

Today’s Activity
  • Laid 1,800 square feet of paving stones in upper patio.
  • Completed wall at entrance of upper patio.
  • Started wing walls for upper patio fireplace.
  • Drafted initial site access plan for lower patio/ramp area.
Tomorrow’s Planned Activities
  • Install low voltage lighting for upper patio.
  • Finish laying paving stones in upper patio.
  • Start capping upper patio sitting wall.
  • Construct remainder of upper patio fireplace wing walls.
  • Review site access plan for next phase.
  • Draft early warning signs for next phase.

Current Safety Concerns

  • No new issues. Lots of stone cutting. Ear plugs, face masks in constant use.
  • Reviewing access plan for work on lower patio and ramp area.

Material Deliveries Scheduled

No deliveries scheduled for Saturday.

Comments

Weather reports are for rain on Sunday, Monday and possibly Tuesday. Work schedule approved for Saturday 7:30 to dusk. Weather permitting, we plan on starting work on the lower patio/ramp area on Thursday or Friday of next week, eliminating access from the breezeway through the Courtyard. We will begin posting early warning notices Monday.

Please expect the breezeway access to the Courtyard to be eliminated from late next week through the Christmas holidays, reopening in January—weather permitting us to maintain a heavy work schedule throughout December.