Monday, December 10, 2007

Progress Report: December 9, 2007

Today’s Activities

  • Cleaned and secured walkways across left side and center of Courtyard.
  • Finished grill and cupboard doors for outdoor kitchen for upper patio.
  • Completed veneering outdoor fireplace for upper patio.
  • 99% completed upper patio.
  • Completed excavation for lower left patio.
  • Post signs for closing of rear Breezeway entrance/exit and temporary ramp to Courtyard.

Tomorrow’s Planned Activities

  • Put finishing touches on upper patio.
  • String line and measure tops of pipes and other underground structures below lower left patio area.
  • Evaluate challenges disclosed by lower left patio excavation.
  • Decide on footprint for lower left patio.
  • Begin demolition of stairs and center area for ramp.

Current Safety Concerns

None.

Material Deliveries Scheduled

  • Multiple flat beds and dump trucks.
  • We will soon place a dumpster on the staging area.

Comments

  • We are working tomorrow, Monday, Dec. 10, from early morning until the rain stops us.
  • Only finishing touches needed for upper patio.
  • Rear Breezeway exit/entrance and temporary ramp closed indefinitely.

Go to our website, www.YellowRibbonFund.org, to see pictures of progress.