Today’s Activities
- Finished trim around upper patio, made area around patio accessible.
- Filled trenches for electrical lines for upper patio.
- Top dressed, graded and seeded area where temporary sidewalk was removed.
- Finished capping wall for upper patio.
- Installed grill for outdoor kitchen for upper patio.
- Initiated veneering outdoor fireplace for upper patio.
- Started excavating for lower left patio.
Tomorrow’s Planned Activities
- Post signs for closing of rear Breezeway entrance/exit and temporary ramp to Courtyard.
- Complete veneering outdoor fireplace for upper patio.
- Put finishing touches on upper patio.
- Clean and secure walkways across left side and center of Courtyard.
- Evaluate challenges disclosed by lower left patio excavation.
Current Safety Concerns
None.
Material Deliveries Scheduled
- None Sunday.
- Multiple flat beds and dump trucks, possibly dumpster, on Monday.
Comments
- We are working tomorrow, Sunday, Dec. 9, from early morning until the rain stops us.
- Temporary sidewalk no longer needed.
- Permanent sidewalk has full access at all times.
- Only finishing touches needed for upper patio.
- Rear Breezeway exit/entrance and temporary ramp will be closed indefinitely.