Sunday, December 9, 2007

Progress Report: December 8, 2007

Today’s Activities

  • Finished trim around upper patio, made area around patio accessible.
  • Filled trenches for electrical lines for upper patio.
  • Top dressed, graded and seeded area where temporary sidewalk was removed.
  • Finished capping wall for upper patio.
  • Installed grill for outdoor kitchen for upper patio.
  • Initiated veneering outdoor fireplace for upper patio.
  • Started excavating for lower left patio.

Tomorrow’s Planned Activities

  • Post signs for closing of rear Breezeway entrance/exit and temporary ramp to Courtyard.
  • Complete veneering outdoor fireplace for upper patio.
  • Put finishing touches on upper patio.
  • Clean and secure walkways across left side and center of Courtyard.
  • Evaluate challenges disclosed by lower left patio excavation.

Current Safety Concerns

None.

Material Deliveries Scheduled

  • None Sunday.
  • Multiple flat beds and dump trucks, possibly dumpster, on Monday.

Comments

  • We are working tomorrow, Sunday, Dec. 9, from early morning until the rain stops us.
  • Temporary sidewalk no longer needed.
  • Permanent sidewalk has full access at all times.
  • Only finishing touches needed for upper patio.
  • Rear Breezeway exit/entrance and temporary ramp will be closed indefinitely.