Progress Report: December 7, 2007

Today’s Activities
  • Installed sod.
  • Installed doors for outdoor kitchen.
  • Cleaned, washed all sidewalks; removed temporary sidewalk.
  • Continued to install electric line and outlets for kitchen.
  • Back filled portion of trenches for electrical lines.
Tomorrow’s Planned Activities
  • Top dress, grade and seed area where temporary sidewalk was removed.
  • Finish capping wall; Sweep joint sand for pavers and tamp.
  • Complete installation of electric lines and outlets for kitchen.
  • Install grill for outdoor kitchen.
  • Begin veneering outdoor fireplace.
  • Complete backfilling trenches for electrical lines.
  • Start excavating for bottom patio.
  • Post signs for closing of rear Breezeway entrance/exit and temporary ramp to Courtyard.
Current Safety Concerns

None.

Material Deliveries Scheduled
  • None tomorrow.
  • Multiple flat beds and dump trucks, possibly dumpster, on Monday.

Comments

  • Temporary sidewalk no longer needed. Permanent sidewalk has full access at all times.
  • Rear Breezeway exit/entrance and temporary ramp will be closed indefinitely starting tomorrow.
  • Only finishing touches needed for upper patio.