Saturday, December 8, 2007

Progress Report: December 6, 2007

Today’s Activities
  • Short work day due to snow cover—most activities snowed out.
  • Completed trench for electrical lines around upper patio.
  • Prepped ground for laying sod.

Tomorrow’s Planned Activities

WEATHER PERMITTING—BUSY DAY

  • Install doors and grill for outdoor kitchen for upper patio.
  • Install electrical lines around upper patio, complete capping of sitting wall.
  • Sod around upper patio.
  • Complete sanding for upper patio surface.
  • Lay out lines for lower patios/ramp.
Current Safety Concerns

Snow, slippery surfaces. WATCH YOUR STEP around work site.

Material Deliveries Scheduled
  • Sod delivered today.
  • Many deliveries put off until tomorrow.
  • Veneer stone and caps on small Ernest Maier flatbed truck.
  • Doors and grill for outdoor kitchen.
Comments
  • Snow caused us to put all work off most of yesterday and today.
  • We must work Saturday and Sunday, to finish the upper patio this week.
  • Snow has delayed veneering fireplace until the weekend.
  • We will begin work on lower patio/ramp area on Sunday or Monday.
  • Prepare for closure of breezeway for work on lower patio/ramp area Sunday or Monday.