- Short work day due to snow cover—most activities snowed out.
- Completed trench for electrical lines around upper patio.
- Prepped ground for laying sod.
Tomorrow’s Planned Activities
WEATHER PERMITTING—BUSY DAY
- Install doors and grill for outdoor kitchen for upper patio.
- Install electrical lines around upper patio, complete capping of sitting wall.
- Sod around upper patio.
- Complete sanding for upper patio surface.
- Lay out lines for lower patios/ramp.
Snow, slippery surfaces. WATCH YOUR STEP around work site.
Material Deliveries Scheduled
- Sod delivered today.
- Many deliveries put off until tomorrow.
- Veneer stone and caps on small Ernest Maier flatbed truck.
- Doors and grill for outdoor kitchen.
- Snow caused us to put all work off most of yesterday and today.
- We must work Saturday and Sunday, to finish the upper patio this week.
- Snow has delayed veneering fireplace until the weekend.
- We will begin work on lower patio/ramp area on Sunday or Monday.
- Prepare for closure of breezeway for work on lower patio/ramp area Sunday or Monday.
No comments:
Post a Comment