- Excavated by hand location of steam pipe that runs through lower patio.
- All other activities snowed out.
Tomorrow’s Planned Activities
WEATHER PERMITTING
- Install doors and grill for outdoor kitchen for upper patio, if equipment arrives.
- Complete trench for electrical lines around upper patio.
- Complete sanding for upper patio surface.
- Lay out lines for lower patios/ramp.
Snow, slippery surfaces. WATCH YOUR STEP around work site.
Material Deliveries Scheduled
- All deliveries from today rescheduled for tomorrow.
- Veneer stone on small Ernest Maier flatbed truck.
- Doors and grill for outdoor kitchen.
- Final caps and finishing materials for upper patio.
Comments
- Snow caused us to put all work off for one complete day.
- We must work Saturday and Sunday, to finish the upper patio this week.
- Snow has delayed veneering fireplace until the weekend.
- We will begin work on lower patio/ramp area on Sunday or Monday.
Prepare for closure of breezeway for work on lower patio/ramp area Sunday or Monday.