Progress Report: December 3, 2007

Today’s Activities
  • Install wiring for low voltage lights and some low voltage lights in upper patio.
  • Begin to cap sitting wall for upper patio.
  • Install firebrick in outdoor fireplace for upper patio.
  • Excavate by hand to locate steam pipe that runs through lower patio.
  • Review hand railing detail and placement for entire Courtyard.
Tomorrow’s Planned Activities
  • Finish installing low voltage lighting and capping wall for upper patio.
  • Install doors and grill for outdoor kitchen for upper patio.
  • Begin veneering outdoor fireplace for upper patio.
  • Locate propane tanks for outdoor fireplace for upper patio.
  • Locate steam pipe in lower patio area and excavate around entire pipe.
  • Evaluate electrical conduit requirements for entire program.
Current Safety Concerns

None.

Material Deliveries Scheduled
  • Veneer stone on small Ernest Maier flatbed truck.
  • Two loads of topsoil on Ernest Maier small dump truck.

Comments

  • Cold weather will not keep us from finishing the upper patio this week.
  • Good luck (so far) in avoiding disruption or change in lower patio plan from subterranean steam pipe.
  • We appear to be on track to begin work on lower patio/ramp area this Wednesday or Thursday.
  • Prepare for closure of breezeway for work on lower patio/ramp area.
  • Please expect the breezeway access to the Courtyard to be eliminated from late next week through the Christmas holidays, reopening in January—weather permitting us to maintain a heavy work schedule throughout December.