Sunday, December 30, 2007

Progress Report: December 28, 2007

Today’s Activities

  • Although it’s been a light week, we had a day of good progress.
  • Completed 95% of the walls for lower left patio and west walls for ramp.
  • Completed outdoor kitchen for lower left patio.
  • Dug drainage ditches for lower left patio.
  • Resolved sheathing issues for conduit pipes below surface of lower left patio.
  • Completed excavation for ramp.

Tomorrow’s Planned Activities

  • No work for the next 4 days—Happy New Year.
  • Next Wednesday, weather permitting, complete construction of walls for lower left patio and west side of ramp.
  • Install drainage for lower left patio.
  • Prep ground for base for lower left patio.

Current Safety Concerns

  • None.
  • Cold weather precautions in place.
  • Continue to expect heavy loads of material during all work days in January.

Material Deliveries Scheduled

No deliveries scheduled until next Wednesday, January 2.

Comments

  • No work for four days.
  • We are taking cold weather precautions for the work crew.
  • We will have a full crew resuming work on January 2, 2008, with heavy work schedules until completion of lower left patio and ramp.

No comments: