- Another day of good progress.
- Almost completed walls for lower left patio and west walls for ramp.
- Completed basic construction of outdoor kitchen for lower left patio.
- No work for the next 4 days—Merry Christmas.
- Next Wednesday, weather permitting, continue construction of walls for ramp.
- Prep ground for base for lower left patio.
Continue to expect heavy loads of material. Lots of truck traffic at staging area.
Material Deliveries Scheduled
No deliveries scheduled until next Wednesday, December 26.
Comments
No work for four days.
We are taking cold weather precautions for the work crew.
We will have a light crew during the rest of Christmas week.
We will have a full crew resuming work on January 2, 2008.