Progress Report: December 20, 2007

Today’s Activities

  • Another day of good progress.
  • Continue building walls for lower left patio and west walls for ramp.
  • Began construction of outdoor kitchen for lower left patio.
  • Finalize plans for both lower patios and ramp.

Tomorrow’s Planned Activities

  • Continue construction for kitchen in lower left patio.
  • Continue construction of walls for ramp.

Current Safety Concerns

  • None. Cold weather precautions in place.
  • Continue to expect heavy loads of material. Lots of truck traffic at staging area.

Material Deliveries Scheduled

No deliveries scheduled tomorrow.

Comments

  • We are taking cold weather precautions for the work crew.
  • We will work tomorrow and take off a long pre-Christmas weekend and then Christmas day. We will have a light crew during the rest of Christmas week, with a full crew resuming work on January 2.