Wednesday, December 19, 2007

Progress Report: December 17, 2007

Today’s Activities
  • Great progress today, a little cold but clear.
  • Finished the gravel base for all walls on lower left patio.
  • Continued digging footers for the walls for the ramp.
  • Finished installing drain pipes for lower left patio.
Tomorrow’s Planned Activities
  • Continue building walls for lower left patio.
  • Continue digging footers for the walls for left side of ramp, once final length has been determined.
  • Repair and cover pipes below surface of patio.
Current Safety Concerns
  • None. Cold weather precautions in place.
  • Continue to expect heavy loads of material. Lots of truck traffic at staging area.

Material Deliveries Scheduled

  • Heavy loads of gravel (22 tons) and stone (10 tons) for filling lower patio area will be coming on a regular basis.
  • We will begin to haul out the dirt that we cannot use on the project.

Comments

  • We are taking cold weather precautions for the work crew.
  • Expect staging area to be full of material for the next several weeks.
  • If the weather holds good for us, we hope to have the walls for the lower left patio and for the ramps up by mid-week, enabling us to work on the base for the paving stones.

No comments: