Saturday, December 15, 2007

Progress Report: December 14, 2007

Today’s Activities
  • No work yesterday, 13 December 2007—great progress today.
  • Dug footers and laid gravel for over 75% of wall in lower left patio.
  • Dug footers and laid gravel for footers on one ramp wall.
  • Installed drain pipes for lower left patio.
Tomorrow’s Planned Activities
  • No work planned on weekend.
  • Depending on the weather, we will finish the gravel base for all walls in lower left patio.
  • Depending on the weather, we will continue doing the walls for the ramp.
Current Safety Concerns
  • None.
  • Heavy loads of material expected soon. Lots of truck traffic at staging area.
Material Deliveries Scheduled
  • We will soon place a dumpster on the staging area.
  • Heavy loads of gravel and stone for filling lower patio area will be coming on a regular basis.
  • We will begin to haul out the dirt that we cannot use on the project.
Comments
  • No work on the weekend.
  • Expect staging area to be full of material for the next several weeks.
  • If the weather holds good for us, we hope to have the walls for the lower left patio and for the ramps up by mid-week, enabling us to work on the base for the paving stones.

No comments: