Thursday, December 13, 2007

Progress Report: December 11, 2007

Today’s Activities

  • Very light workload today.
  • Cleaned staging area in preparation for heavy deliveries of material for lower patio area.
  • Put finishing touches on fireplace and outdoor kitchen for upper patio.
  • Completed installation of electrical outlets for upper patio.

Tomorrow’s Planned Activities

  • Finished cleaning area around upper patio.
  • Begin digging footers for wall in lower left patio and begin excavation of ramp area.

Current Safety Concerns

  • None.
  • Heavy loads of material expected soon. Lots of truck traffic at staging area.

Material Deliveries Scheduled

  • We will soon place a dumpster on the staging area.
  • Heavy loads of gravel and stone for filling lower patio area will be coming on a regular basis.

Comments

  • Expect staging area to be full of material for the next several weeks.
  • We appreciate the allocation of three parking spaces for our crew for the next six weeks.