Progress Report: December 10, 2007

Today’s Activities

  • Light construction workload due to rain and final decision-making on lower patio.
  • Finished electrical outlets for outdoor kitchen for upper patio.
  • String lined and measured tops of pipes and other underground structures below lower left patio area.
  • Evaluated same with WRAMC DPW staff.
  • Decided on footprint for lower left patio.
  • Post signs for closing of rear Breezeway entrance/exit and temporary ramp to Courtyard

Tomorrow’s Planned Activities

  • Depending on weather, prepare for placing footers for walls on left lower patio.
  • Finish cleaning area around upper patio.

Current Safety Concerns

None.

Material Deliveries Scheduled

  • Multiple flat beds and dump trucks.
  • We will soon place a dumpster on the staging area.

Comments

  • Thanks to WRAMC DPW staff for timely and thorough evaluation of site issues.
  • Work depends on rain, for tomorrow and the next day.
  • Only finishing touches needed for upper patio.
  • Rear Breezeway exit/entrance and temporary ramp closed indefinitely.