Friday, November 30, 2007

Progress Report: November 29, 2007

Today’s Activities
  • Completed installation of seat wall for upper patio.

  • Completed drain pipes and drainage system for upper patio.

  • Completed installation of all base material for paving stones.

  • Put in base block for wall at entrance of upper patio.

  • Completed outdoor kitchen island.

  • Completed backfill outside of wall with top soil and grade.

  • Reviewed construction drawings for lower patio/ramp area.

Tomorrow’s Planned Activities

  • Install low voltage lighting for upper patio.

  • Lay paving stones in upper patio.

  • Construct remainder of upper patio fireplace wing walls.

  • Layout lower patio/ramp area. Draft initial site access plan for next phase.

  • Start capping upper patio sitting wall.

Current Safety Concerns


No new issues. Preparing access plan for work on lower patio and ramp area.

Material Deliveries Scheduled


At least one more truck of paving stones to arrive on Ernest Maier flat bed.

Comments

Weather reports are for rain on Sunday, Monday and possibly Tuesday. We plan on working Saturday 7:30 to dusk and perhaps Sunday if it does not rain. We plan on starting work on the lower patio/ramp area on Wednesday or Thursday of next week, which will mean cutting access from the breezeway through the Courtyard. We will begin posting notices this weekend.