- Firebox for fireplace installed.
- Chimney started.
- Installation of seat wall nearly complete.
- Backfill outside of wall w/top soil and grade.
- Continue w/building of outdoor kitchen island.
Tomorrow’s Planned Activities
- Start to install low voltage lighting
- Continue to backfill patio portion of project w/crushed stone and compact
- Construct remainder of fireplace chimney & wing walls
- Screed sand and start laying pavers
- Layout lower patio/ramp area
- Start capping sitting wall
Current Safety Concerns
Reviewed ear protection requirements w/all employees when using saws or other equipment. Ear plugs were provided again to all employees.
Material Deliveries Scheduled
At least one truck of pavers to arrive on Ernest Maier flat bed