- Installation of upper patio seat wall continues.
- Continue to backfill for patio portion of project with crushed stone and compact.
- Started running wiring for low voltage lighting for upper patio.
Tomorrow’s Planned Activities
- Comcast Network crew on site to begin filming as TV special episode of American Builder.
- Continue with seat wall installation for upper patio.
- Continue to backfill for patio portion of project with crushed stone and compact.
- Continue running wiring for low voltage lighting and install lights for upper patio.
Current Safety Concerns
Nothing new at this time.
Material Deliveries Scheduled
No deliveries scheduled for tomorrow.
Comments
Beautiful weather. We are on schedule to complete the upper patio project by beginning of next week.
Once we complete the upper patio project, we will begin on the lower patios and the ramp leading from the Mologne House breezeway to the Courtyard. We will be closing off the breezeway entrance/exit to the Courtyard, but the breezeway will be open and the entrance/exit to the parking lot will remain open. We will provide a new access map by the end of the week and post appropriate signs in advance.
No comments: