Monday, November 26, 2007

Progress Report: November 26, 2007

Today’s Activities

  • Upper patio fireplace base plate set.
  • Installation of upper patio seat wall continues.
  • Continue to backfill for patio portion of project with crushed stone and compact.
  • Drainage system installation for upper patio complete.
  • Started running wiring for low voltage lighting for upper patio.

Tomorrow’s Planned Activities

  • Continue with seat wall installation for upper patio.
  • Continue to backfill for patio portion of project with crushed stone and compact.
  • Continue running wiring for low voltage lighting and install lights for upper patio.

Current Safety Concerns

Nothing new at this time.

Material Deliveries Scheduled

Numerous dump trucks with crushed and clean stone in Ernest Maier Trucks.

Comments

Rain was a minor factor today. We are on schedule to complete the upper patio project by beginning of next week if not sooner.

Col Haselden visited the site and gave very encouraging words to the Site Manager which he passed on to the crew at lunch time. The workers are very pleased to see the soldiers, Marines and their families watching the progress of the work, especially on the weekend. They expressed their respect and admiration for the residents of Mologne House and Walter Reed Army Medical Center.