Today’s Activities
- Fireplace footer for upper patio completed.
- Installation of seat wall for upper patio started.
- Continue with installation of drainage for upper patio.
Tomorrow’s Planned Activities
- Continue with seat wall installation for upper patio.
- Complete drainage for upper patio.
- Continue to backfill patio portion of project w/crushed stone and compact for upper patio.
- Start running wiring for low voltage lighting for upper patio.
Current Safety Concerns
Nothing new at this time. We expect many deliveries tomorrow, and we expect a rainy day.
Material Deliveries Scheduled
- Numerous dump trucks with crushed and clean stone.
- We are alert to rainy weather, and we expect a lot of activity.
Comments
- Quiet weekend from the residential standpoint, good progress on the site.
- Rain likely on Monday and probably on Tuesday, as noted above.
- Work will continue as long as it is not a heavy rain.
- Nice visit from Peter Anderson on Sunday afternoon.
- Thanks for the good words to the crew.