Sunday, November 25, 2007

Progress Report: November 25, 2007

Today’s Activities

  • Fireplace footer for upper patio completed.
  • Installation of seat wall for upper patio started.
  • Continue with installation of drainage for upper patio.

Tomorrow’s Planned Activities

  • Continue with seat wall installation for upper patio.
  • Complete drainage for upper patio.
  • Continue to backfill patio portion of project w/crushed stone and compact for upper patio.
  • Start running wiring for low voltage lighting for upper patio.

Current Safety Concerns

Nothing new at this time. We expect many deliveries tomorrow, and we expect a rainy day.

Material Deliveries Scheduled

  • Numerous dump trucks with crushed and clean stone.
  • We are alert to rainy weather, and we expect a lot of activity.

Comments

  • Quiet weekend from the residential standpoint, good progress on the site.
  • Rain likely on Monday and probably on Tuesday, as noted above.
  • Work will continue as long as it is not a heavy rain.
  • Nice visit from Peter Anderson on Sunday afternoon.
  • Thanks for the good words to the crew.