Today's Activities
- Upper patio wall installation almost complete.
- Continue with fireplace footer installation.
- Continue with drainage installation.
- Install grill footer block.
Tomorrow's Planned Activities
- Complete drainage installation.
- Complete fireplace footer installation (if block is available).
- Complete wall installation.
- Start backfilling upper patio with crushed stone.
Current Safety Concerns
None. It's quiet at Mologne House this weekend.
Material Deliveries Scheduled
- Nothing on Sunday.
- Monday plan on several loads of crushed and clean stone in Ernest Maier dump trucks.
Comments
Mike Southard looked at the weather forecast on Friday and decided that the possibility of bad weather early next week made work on Saturday and Sunday the right way to stay on schedule. We appreciate the consideration of the Provost Marshal and the residents who did not get away this weekend. Thanks.
No comments:
Post a Comment