- Portion of drain tile installed.
- Footer course for retaining wall installed.
- Geogrid installed as necessary.
- Several courses of retaining wall installed.
- Electrical conduit installed under retaining wall.
- Several courses of block installed for fireplace footer.
- Fencing placed around trees and light poles in construction area, per DPW suggestion.
Tomorrow’s Planned Activities
No work until Monday. Happy Thanksgiving!
Safety Concerns Today
- Added stone to haul route as it was wearing badly with all the machines going back and forth. This will help prevent unnecessary erosion and keep the mud to a minimum.
- Lots of families and children around. Please make sure no one enters the work site and children remain supervised at all times. Everyone likes a good pile of dirt. Thanks for the cooperation.
Material Deliveries
Nothing scheduled over Thanksgiving weekend. Wall block, clean stone and crushed stone scheduled Monday.
Comments
- Please remind everyone that the playground is open and will stay open during the entire construction process. All families and children are welcome there—PLAYGROUND IS NOT ON WORK SITE.
- Great progress in short work week. A couple of days of great weather, a hardworking crew, constructive advice from the WRAMC project manager and DPW team, safety and environmental personnel, and the wounded warriors and their families staying at Mologne House, Delano Hall, and the Fisher Houses.