Monday, November 19, 2007

Progress Report: November 18, 2007

We have the following activities planned for November 19, 2007:
  • Equipment & material deliveries.
  • Material staging.
  • Install safety fencing and temporary sidewalks.
  • Tree removal. Layout of patios.
  • Excavation may start, depending on overall progress.

Deliveries scheduled:

  • Contractor equipment and trailers between about 0700 and 0800.
  • Small pick up truck w/miscellaneous safety items between about 0730 and 0830.
  • Small flat bed truck w/drainage products, rebar, etc., between about 1000 and 1200.
  • Tri axle dump truck w/crushed stone between about 1000 and 1200.
  • Tri axle dump truck w/clean stone between 1300 and 1500.


Malone map



Current Safety Concerns:

  • Be aware of delivery vehicles when walking or driving between Mologne House and the gym.
  • Be aware of construction equipment moving in the Mologne House Courtyard (rear of building).
  • Please abide by safety/flag men when walking or driving in any of the construction areas.
  • Please do not enter the marked construction or material staging areas for any reason.
  • Breezeway exit to Courtyard/temporary ramp will be closed during tree removal from approximately 0800 until 1300. Exit from 2nd level will remain open as will breezeway entrance/exit to parking lot (front of building). The breezeway itself will remain open the entire time.
  • Portion of the sidewalk from 2nd level exit to the courtyard will be closed after tree removal is complete until the end of work for the day. A temporary sidewalk will be available in that area at all times. The permanent walk will remain open during all non construction hours (approximately 1800 to 0730 next day).
  • Please be aware of, and follow, the numerous safety signs, fencing and cones throughout the area.

No comments: