- Equipment & material deliveries.
- Material staging.
- Install safety fencing and temporary sidewalks.
- Tree removal. Layout of patios.
- Excavation may start, depending on overall progress.
Deliveries scheduled:
- Contractor equipment and trailers between about 0700 and 0800.
- Small pick up truck w/miscellaneous safety items between about 0730 and 0830.
- Small flat bed truck w/drainage products, rebar, etc., between about 1000 and 1200.
- Tri axle dump truck w/crushed stone between about 1000 and 1200.
- Tri axle dump truck w/clean stone between 1300 and 1500.
Current Safety Concerns:
- Be aware of delivery vehicles when walking or driving between Mologne House and the gym.
- Be aware of construction equipment moving in the Mologne House Courtyard (rear of building).
- Please abide by safety/flag men when walking or driving in any of the construction areas.
- Please do not enter the marked construction or material staging areas for any reason.
- Breezeway exit to Courtyard/temporary ramp will be closed during tree removal from approximately 0800 until 1300. Exit from 2nd level will remain open as will breezeway entrance/exit to parking lot (front of building). The breezeway itself will remain open the entire time.
- Portion of the sidewalk from 2nd level exit to the courtyard will be closed after tree removal is complete until the end of work for the day. A temporary sidewalk will be available in that area at all times. The permanent walk will remain open during all non construction hours (approximately 1800 to 0730 next day).
- Please be aware of, and follow, the numerous safety signs, fencing and cones throughout the area.